Capital Improvements

Sugarmill Elementary School

History & Background

  • Ses Opened August 1997.

  • Original Building Is 82,673 Square Feet.

  • 40 Original Instructional Spaces.

  • Original Building Capacity Is 800fte (Students).

Description

  • The Addition Added 9
    Instructional Spaces And New

  • Boys/girls Restrooms.

  • New Addition Brings Capacity To 980 Fte (Students).

  • Addition Brings An Additional10,200 Square Feet.

Timeline

  • Construction Began December

    2022 On Addition

  • Completed Construction

  • August 2023 For Renovation And Addition.

  • Punch List Items To Be Completed Fall 2023.

Project Updates

  • Parking Lot Completed.

  • Ac For Media Center Expected
    Thanksgiving Break.

  • Cleanup In Progress.

  • Front Canopy Soffit On Order.

  • Final Grading And Site Work In Progress.

school hall

school building

PSA Baseball / Softball Fields

History & Background

  • Original Fields Constructed 1998.

Description

  • Both Fields To Recieve New Dugouts.

  • All Ture Surfaces.

  • New Bullpens.

  • New Fencing And Safety Netting

  • And Backstops.

Timeline

  • Baseball Field Construction
    Expected To Start Week Of September 11.

  • Baseball Field Completion By
    February 1st.

  • Softball Field Started
    October 20.

  • Softball Completion Expected To Take 5 Months From Start.

Project Updates

  • Baseball Backstop Wall And Dugouts Under Construction.

  • Softball Field Is Currently
    Cleared And Ready For Drainage.

  • Drainage For Baseball Is Underway.

land on construction

land on construction

land on construction

Kingsland Elementary School

History & Background

  • Kes Opened August 1994.

  • Original Building Is 71,715 Square Feet.

  • 35 Instructional Spaces.

  • First Full Renovation

Description

  • Plan To Complete Full Renovation To Include; Floors, Plumbing, Paint, Eru's, All New Ptac Units, Mill Work, Spray Foam Insulation, Reconfigure

  • Front Office, Tile Work, Updated Water Fountains, And Resurface The Parking Lot.

Timeline

  • Construction Expected To Begin May 23, 2024

  • Expected To Be Complete Prior To Fy25 School Year Start.

Project Updates

  • In The Initial Stages Of Planning.

  • Mechanical And Electrical

  • Walkthroughs Complete And Planning Is In Progress.

school street sign

ESPLOST Projects

Project Name

Proposed Budget

Year

Collected

Thru 06/30/24

Job Completion Percentage

Expected CapitolOutlay

Local Cost

Status

IT Roof Repair

$ 20,000.00

FY 25

Pending

Central Office Roof Replacement

$ 265,000.00

FY 25

Pending

CCHS Canopies

$ 1,300,000.00

FY 25

Pending

CMS Roof Replacement

$ 1,300,000.00

FY 25

$ 936,396.00

$ 363,604.00

Pending

Band Equipment - 2 Middle Schools & High School

$ 500,000.00

FY 25

Pending

Coastal Bldg Paint/Carpet

$ 150,000.00

FY 26

Pending

SMES Paint

$ 500,000.00

FY 26

Pending

NGC Café Restroom Addition

$ 265,875.00

FY 26

Pending

NGC Window Replacement

$ 80,000.00

FY 26

Pending

CMS Weight Room.Locker Room

$ 1,100,000.00

FY 26

Pending

CMS Athletic Dugout Fencing/Fields

$ 600,000.00

FY 26

Pending

Mowers/Graders Middle Schools

$ 30,000.00

FY 26

...

Pending

LED Lighting Upgrade SMES/SMIMS/NGC

$ 500,000.00

FY 26

Pending

Mamie Lou Gross Renovation

$ 6,000,000.00

FY 27

$ 1,412,477.00 $ 4,587,523.00

Pending

CCHS Multipurpose Indoor Facility

$ 9,500,000.00

FY 27

Pending

CCHS CTAE Annex

$ 5,000,000.00

FY 28

Pending

NGC Renovation Building 5030

$ 8,000,000.00

FY 28

$ 1,105,056.00 $ 6,894,944.00

Pending

Annual Reocurring Expenses

Project Name

Budget Type

Amount

Technology

Annual Budget

$587,845.000

Network upgrades

Annual Budget

$98,140.000

Network upgrades

Annual Budget

$709,500.000

Chromebooks

Annual Budget

$12,500.000

Instructional Textbooks

Annual Budget

$1,038,700.000

School Buses

Annual Budget

$299,823.620

PTAC Unit Replacements

Annual Budget

$800,000.000

Bleacher Repairs

Annual Budget

$60,000.000

Furniture - Districtwide

Annual Budget

$25,000.000

Capitol Project Emergency

Annual/Contingency

$110,000.000

Total per year

$3,991,509.000

Total cost ESPLOST FY24-FY28

$19,957,545.00